Proposed Construction/custom Woes

Status
Not open for further replies.

KYLECODY

Senior Member
Joined
Apr 26, 2003
Professional Status
Certified Residential Appraiser
State
Arizona
Completed a nice proposed construction on an acre lot to plans/specs in August based on the cost sheets provided, contract price roughly 500k.

Now 3 months later the owner has decided to do about 75k worth of work themselves (full landscaping on an acre lot, paver driveway, block fencing, etc) and they have reduced the contract.

Of course the effective date is 8/20 and now with the significant change I will need to go back in and readjust the grid, see if there are any other comps, etc. and my opinion of value will change significantly.

My current thought is to keep the original effective date, note the significant change in price, readjust the grid and adjust opinion of value and charge accordingly. Or does the fact that this will change value significantly mean I need a new effective date and new report/fee? Just one more reason why I generally stay away from these deals. Any thoughts?
 
Why would you need new comp's if they're going to do the same work Quality with the same plans and specs? Wouldn't it be worth the same on the market if it was the same house and same quality as the original plans and specs Builder? Or is there $75,000 worth of Market variance between the original and the new plans?
 
Why would you need new comp's if they're going to do the same work Quality with the same plans and specs? Wouldn't it be worth the same on the market if it was the same house and same quality as the original plans and specs Builder? Or is there $75,000 worth of Market variance between the original and the new plans?

They are no longer doing landscaping, fencing or a paver driveway. On acre lots in this custom home area the difference between a fully landscaped and block fenced lot versus no landscaping or block fencing is significant. I would be searching for additional custom sales on acre lots with no landscaping or fencing to support the needed adjustment.
 
Not everything has to be bracketed, just supported. Chats with the local re professionals can be a big help in supporting the contributory value.
 
Completed a nice proposed construction on an acre lot to plans/specs in August based on the cost sheets provided, contract price roughly 500k.

Now 3 months later the owner has decided to do about 75k worth of work themselves (full landscaping on an acre lot, paver driveway, block fencing, etc) and they have reduced the contract.

Of course the effective date is 8/20 and now with the significant change I will need to go back in and readjust the grid, see if there are any other comps, etc. and my opinion of value will change significantly.

My current thought is to keep the original effective date, note the significant change in price, readjust the grid and adjust opinion of value and charge accordingly. Or does the fact that this will change value significantly mean I need a new effective date and new report/fee? Just one more reason why I generally stay away from these deals. Any thoughts?
I would ask for it to be a new assignment with a new current effective date. Back in August you appraised it based on a certain set of plans and specs. Price aside, they've substantially change the specs and plans , and you might need new comps as well as cost approach etc
 
Not everything has to be bracketed, just supported. Chats with the local re professionals can be a big help in supporting the contributory value.

I understand, this will drop my opinion of value roughly 50kish. Just trying to decide how many changes I'm willing to do on a report with an effective date of 2.5 months ago and requesting a small fee versus a new assignment with new effective date at a new fee.
 
I understand, this will drop my opinion of value roughly 50kish. Just trying to decide how many changes I'm willing to do on a report with an effective date of 2.5 months ago and requesting a small fee versus a new assignment with new effective date at a new fee.

Why not ask for a new eff date and new assignment? Nothing to be gained by keeping the old eff date would need a complete re work if you do
 
On acre lots in this custom home area the difference between a fully landscaped and block fenced lot versus no landscaping or block fencing is significant. I would be searching for additional custom sales on acre lots with no landscaping or fencing to support the needed adjustment.
Based on this and what you've mentioned I think I agree with JG
I would ask for it to be a new assignment with a new current effective date. Back in August you appraised it based on a certain set of plans and specs. Price aside, they've substantially change the specs and plans , and you might need new comps as well as cost approach etc
The SOW/plans & specs seem to have changed, at least significantly enough (50kish per your comment) that it may affect your original OMV.

This sounds like it may require a new(er) analysis 2 1/2 months later, in which case may require (or not) a separate fee (this becomes a business decision. But from what I read from the post(s), at least a new search of comps should be done to see if the changes really are "50kish" as you state. That's my $0.02
 
Status
Not open for further replies.
Find a Real Estate Appraiser - Enter Zip Code

Copyright © 2000-, AppraisersForum.com, All Rights Reserved
AppraisersForum.com is proudly hosted by the folks at
AppraiserSites.com
Back
Top