I recently did a 1004D final inspection and there were a few items in Escrow Holdback; Final Grade, driveway, bury sump line.
I did the inspection and marked the form as Complete, although these items were not finished. The lender has come back and asked me to update the 1004D to reflect the escrow holdback items still need to be completed. Do I change the 1004D inspection to Incomplete and uncheck the "Certificate of Completion" box? Do I note these items in the paragraph below? Please help. Thanks.
I did the inspection and marked the form as Complete, although these items were not finished. The lender has come back and asked me to update the 1004D to reflect the escrow holdback items still need to be completed. Do I change the 1004D inspection to Incomplete and uncheck the "Certificate of Completion" box? Do I note these items in the paragraph below? Please help. Thanks.