Anyone who does proposed construction assignments has dealt with this on some level. They order the final and the finished product is different than plans. If it’s minor, no problem, but what do you do when the heated area is 15% more? 15% less? What if they add a finished room over the garage? Turn a covered porch area into a finished sunroom? I have one where they changed the garage from a front entry garage to side entry and added 154 more square feet which is basically just more storage area in what is still a 2 car garage. I’m going to simply make a comment about the garage being larger than plans and specs, but is still a 2 car garage and stick a fork in it, it’s done IMO. I’ll also include a revised sketch. I asked a peer and he said, oh, no you need to stop the entire lending freight train, wave a lantern, call underwriting 911, alert the lender, new report, etc. What say the experts?