foundation, walls, windows, doors, roof - no interior finishes.
How could you have completed an as-is appraisal with no interior finish, for new construction? Maybe your area is different than mine, but the only time an as-is appraisal is completed around here on an SFR with no interior finish is when it's an REO/foreclosure/repossession and they're usually just interested in liquidation value.
And if you did actually complete an as-is appraisal on it with no interior finish, why would they need an UPDATE to say that it's worth the same now that it's completely finished? Unless the market had a huge 30%+ downward spiral in the past few 5 months, on what planet would a completely finished new construction not be worth as much as a shell from 5 months ago?
Maybe you just haven't explained things well enough here or maybe I'm just not understanding them properly, but here's the normal sequence of events that happens when you complete an appraisal based on plans / specs for started / unstarted new construction:
1. You receive details plans / specs that specify information on the quality of materials, design, size, room counts, etc. The plans / specs need to have enough detail that you can get a good idea of what is being constructed. This works well in cookie-cutter subdivisions where they can sometimes point at the previous home and say that it's going to be very similar to that one (material, construction technique, quality, etc), with these certain listed changes.
2. You base your appraisal on a HYPOTHETICAL SITUATION (HS) that the entire house was actually completed to the standards laid out in the plans / specs received, as of your effective date listed in the appraisal. The effective date is commonly the day you go and first take photos of the vacant land or already started construction. If using URAR form 1004, you would NOT mark the 'as-is' box at the bottom of page 2. You would mark the 'subject to completion per plans and specifications.....' box.
3. The client may have you go out and complete inspections any time between your original inspection date and the completion date. These inspections are usually to let them know the progress of the project. Sometimes the preliminary inspections are used by the bank to give partial payments to the general contractor as certain percentages of the work are completed.
4. At some point the client will be informed that the subject is complete and ready for occupancy / transfer to the buyer. At this time, the client will often order a 1004d where they want you to go out and do a final inspection to make sure that the SFR was built to the plans / specifications that you based your Hypothetical Situation on (#2 above). They are usually just expecting the 2nd checkbox on 1004d for the section titled "Certification of Completion". In that section you explain whether the subject was completed (or not) in accordance with the requirements / conditions stated in your original report (HS). If something differs from the plans / specs, make sure to note it. I've had ones that changed amount of square footage, finished/unfinished basement, etc. It's important to measure the house and do a complete inspection. If you find out that something significant has changed, you don't want the bank basing the value on your appraisal with the HS.
*** I'm taking a wild guess here and thinking you incorrectly completed step #2 above "as-is" instead of as a hypothetical situation. If so, I'd suggest correcting it and resubmitting it to the client with some type of explanation like: "In preparing to do the 1004d final inspection, I noticed that I had a typographical error in my original report where I incorrectly checked the wrong box at the bottom of page #2 of the URAR."