Below is a letter I have received directly from VA last year or the year prior for the situation you may find helpful.
"The 1805 is the appraisers Letter of Engagement and establishes the scope of work requested by the lender. When the 1805 is ordered as “
existing” this means the appraiser can view the subject is
over 1 year since Certificate of Occupancy issued or previously occupied (100% complete is assumed since the Certificate of Occupancy has been issued). This is not an “
existing” order, so it was ordered incorrectly.
If the Lender has ordered the appraisal as
Existing Construction or
New Construction and the Appraiser finds the Property to be Proposed or Under Construction with more than customer preference items remaining, the
appraiser must immediately stop and notify the Lender before proceeding.
The Lender must then decide if the appraisal is to proceed.
If the appraisal is to proceed, the Lender must correct the 1805 which requires the case to be cancelled to allow for a new 1805 appraisal order.
The Denver RLC must be contacted to cancel the previous case per VA/RLC Guidelines.
The Denver RLC may facilitate assigning the new VA case to the same appraiser as would be appropriate.
Regardless of appraiser selection for the new VA case, the appraiser for the previous case is allowed to charge for work completed and/or a trip fee for the previous case.. The Veteran must not be charged for the work completed under the canceled case.
The Lender must upload the required Construction Exhibits to the new VA Case in WebLGY before the appraiser can continue.
If the Appraiser has obtained Construction Exhibits during their normal course of business, the Appraiser may forward these documents to the Lender to allow the Lender must upload them to WebLGY.
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Here is some information about Proposed Construction; Under Construction; New construction.
Appraiser/Industry Standard Definitions:
Existing Construction – Property is 100% complete.
Proposed Construction – Before concrete is poured.
Under Construction – After concrete is poured, but before the Property is 100% complete.
VA Handbook Definitions for the 1805:
Existing Construction – Over 1 year since Certificate of Occupancy issued
or previously occupied (100% complete is assumed since the Certificate of Occupancy has been issued).
New Construction – Under 1 year since Certificate of Occupancy issued
and never occupied,
or complete with the exception of “customer preference” items as defined in Chapter 10 Topic 9. c. below.
Proposed Construction – Can be Proposed (before concrete as per industry standard above) or Under Construction (after concrete per industry standard above).
VA definition of Under Construction differs from industry standard due to the VA New Construction definition above which allows for incomplete customer preference items.
VA allows an appraisal to be completed at any stage of construction.
If the Property is
Under Construction based on industry standards, but
does not meet the VA New Construction definition with only buyer preference items remaining:
The Lender must complete the 1805 indicating
Proposed Construction and the Lender must follow the requirements of Chapter 10 Topic 12.
The Lender must upload construction exhibits for Properties that are Under Construction at the time of the case assignment.
The Appraiser must complete the appraisal subject to plans and specs per Chapter 10 Topic 12 c.; however, the appraisal report will be market
Under Construction on page 1 of the FNMA Form 1004 URAR or FNMA Form 1025 Small Residential Income, or page 2 of the FNMA Form 1004C Manufactured Home.
The Appraiser must have the Certification of Exhibits as per Chapter 10 Topic 12 b.) included in the report.
If the Property is
Under Construction based on industry standards, but
does meet the VA New Construction definition with only buyer preference items remaining:
The Lender must complete the 1805 indicating New Construction and does not need to follow the requirements of Chapter 10 Topic 12.
The Appraiser must complete the appraisal subject to repair as per Chapter 11 Topic 18 b.; however, the appraisal report will be market Under Construction on page 1 of the FNMA Form 1004 URAR or FNMA Form 1025 Small Residential Income, or page 2 of the FNMA Form 1004C Manufactured Home.
The Appraiser does not need to have the Certification of Exhibits as per Chapter 10 Topic 12 b.) included in a report.
If the Lender has ordered the appraisal as Existing Construction or New Construction and the Appraiser finds the Property to be Proposed or Under Construction with more than customer preference items remaining, the appraiser must immediately stop and notify the Lender before proceeding.
The Lender must then decide if the appraisal is to proceed.
If the appraisal is to proceed, the Lender must correct the 1805 which requires the case to be cancelled to allow for a new 1805 appraisal order.
The Denver RLC must be contacted to cancel the previous case per VA/RLC Guidelines.
The Denver RLC may facilitate assigning the new VA case to the same appraiser as would be appropriate.
Regardless of appraiser selection for the new VA case, the appraiser for the previous case is allowed to charge for work completed and/or a trip fee for the previous case.. The Veteran must not be charged for the work completed under the canceled case.
The Lender must upload the required Construction Exhibits to the new VA Case in WebLGY before the appraiser can continue.
If the Appraiser has obtained Construction Exhibits during their normal course of business, the Appraiser may forward these documents to the Lender to allow the Lender must upload them to WebLGY.
It must be noted that “customer preference items” are somewhat subjective.
Those items typically considered as customer preference items are:
- kitchen appliances
- floor covering
- finished fixtures such as door knobs, cabinet handles, interior light fixtures, ceiling fans, bath mirrors, towel racks, etc. Finished fixtures do not include faucets, bath tubs, sinks, cabinets, counter tops.
- All exterior work, including paint, should be completed at the time of appraisal except for those items affected by adverse weather conditions.
VA does not use or expect a percent complete metric in this decision. We will defer to the appraiser’s judgement on the breadth of remaining items and if they fall under “other equipment”. As mentioned, if the appraiser is preparing the appraisal report Subject to Repairs for remaining “customer preference items” Chapter 11 Topic 18 b. applies.
USPAP Compliance by the appraiser:
USPAP Standards Rule 1-2 (e) requires the appraiser to have reliable information to identify the characteristics of the property. Remaining customer preference items must be clearly identified by the appraiser. USPAP Standards Rule 2-2 (a) (iv) requires the appraisal report to contain sufficient information to identify the physical property characteristics relevant to the assignment. Compliance with USPAP compels the appraiser to report remaining customer preference items sufficiently to identify what is yet to be completed."